Oxygen Development

Oxygen Development’s headquarters facility combines manufacturing with their corporate offices. Because the project had an accelerated schedule and the job site was situated directly on a major thoroughfare, requiring that deliveries and equipment not impact traffic, Tilt-Up was the best choice for construction.

The building has a curved feature on the entire frontage with pavers and landscaping that provide an upscale appearance. A curved cast-in-place concrete stairway in the main entry lobby, along with polished concrete floors, gives the office area an industrial, but aesthetically pleasing look. The east side of the building consists of two rows of Tilt-Up panels. The inside row comprises the main building's bearing wall and is curved inward, originating at the ends of both the north and south walls. The outside curved feature row curves outward, originating from the southeast corner of the main wall and continuing on an outward plain, on a segmented radius. This causes some of the east wall panels to be double thickness with openings and architectural recesses on both sides of the wall.

On this segmented curved wall, there are large recesses on the exterior that have a hammered finish in the Tilt-Up panels as well as recessed columns to accommodate a continuous ribbon glass window wall. The curved frontage wall of the building also features a cast-in-place eyebrow above the ribbon windows on both the first and the second floors for the full length of the building's elevation, extending through to the Tilt-Up panel cantilevers on each end.

Oxygen was also required to provide a new covered bus stop shelter along the main road in front of the facility, so one was efficiently designed and erected utilizing Tilt-Up, including the roof. Despite a very tight schedule, Tilt-Up enabled the owner to occupy the building on time, and manufacturing began on schedule.

 
Main banner image for Oxygen Development

Project Location

West Palm Beach, FL 33406
United States

TILT-UP ACHIEVEMENT AWARD

The Tilt-Up Achievement Awards were established to honor projects that use site-cast tilt-up concrete to introduce new building types, advance industry technology and provide unique solutions to building programs. Winning entries illustrate the variety, beauty, and flexibility of tilt-up construction.

ACHIEVEMENT

2012

The world’s greatest tilt-up structures are featured by the TCA as Tilt-Up Achievement Award Winners. Learn more >

Project Images

Search Project Database

TILT-UP TODAY MAGAZINE / PROJECTS IN THE NEWS

Project Team (TCA Members)

General Contractor:
 
Concrete Contractor:
Woodland Tilt-Up
Architect:
 
Engineer:
Permit Engineering Services Inc
Leviat

Project Specifics

Project Category:
Production/Manufacturing
Building Types:
Finishes:
Features:
Insulation:
Environmental:
Number of Floors:
0
Number of Panels:
140 panels
Tilt-Up Wall Area:
91,513 sq ft (8,502 sq m)
Total Floor Area:
221,732 sq ft (20,599 sq m)
Project Footprint:
166,869 sq ft (15,502 sq m)
Tallest Panel:
45 ft 1 in (13.74 m)
Widest Panel:
49 ft 1 in (14.96 m)
Largest Panel:
1,233 sq ft (114.5 sq m)
Heaviest Panel:
176,000 lbs (79,832 kg)
Tallest Cantilever:
12 ft 6 in (3.81 m)
Longest Spandrel:
34 ft 9 in (10.59 m)