This project was characterized by the extremely short duration of six weeks and a limited installation window between 8:30 p.m. and 5:00 a.m. for two nights only, as the panels were erected on the roads in and out of King Shaka's Durban Airport.
There was no feasible in-situ concrete solution to this project. Twenty panels in total were required. Therefore, two phases were created to cast and install ten panels during each phase. The casting surface and show face of the panels were created using concrete Tilt-Up formwork. The panels were flat lifted by two cranes, placed onto specialized Tilt-Up concrete cradles cast at the same radii as the underside of the curved panel, onto trailers.
The panels are curved in two planes, have a moment connection into the base foundation and are cantilevered 11.5m. The Tilt-Up technique was cost-effective, offered savings in program duration and a quality unachievable with conventional building techniques.
Durban, Kwazulu Natal 4000
South Africa
The Tilt-Up Achievement Awards were established to honor projects that use site-cast tilt-up concrete to introduce new building types, advance industry technology and provide unique solutions to building programs. Winning entries illustrate the variety, beauty, and flexibility of tilt-up construction.
ACHIEVEMENT
2011
The world’s greatest tilt-up structures are featured by the TCA as Tilt-Up Achievement Award Winners. Learn more >