The Jefferson County School District had a simple goal: They needed to construct the largest elementary school ever built in their district in record time. When Saunders Construction, which had previously built a Tilt-Up charter school in the same district, came onto the project, the schedule was already tight—but it was made even more so by the decision to use a structural floor over a crawlspace instead of the previously designated slab-on-grade.
An even more concerning issue was the team had already designed into the project interior Tilt-Up walls. In fact, there is not a steel column anywhere in the building.
This choice of a structural floor added nearly seven weeks of design and construction to the project, while the project completion date remained the same. Saunders met the expedited schedule by phasing the panel design and construction to reflect the building’s four quadrants, while design proceeded on the rest of the structure. The new floor style also required 70,000 square feet of casting bed to be erected around the building for panel forming.
The fastest-designed ground-up school ever constructed in the district, the 68,000-square-foot Al Meiklejohn Elementary was built in just ten months and features a host of inviting features, including letters, numbers and musical notes formed from foam cutouts and recessed into the panels, as well as a front entry canopy decorated with laser-cut perforated metal panels shaped like stars, suns and moons.
Arvada, CO 80005
United States
The Tilt-Up Achievement Awards were established to honor projects that use site-cast tilt-up concrete to introduce new building types, advance industry technology and provide unique solutions to building programs. Winning entries illustrate the variety, beauty, and flexibility of tilt-up construction.
ACHIEVEMENT
2007
The world’s greatest tilt-up structures are featured by the TCA as Tilt-Up Achievement Award Winners. Learn more >