Project summary provided by submitting company.

With an overall schedule from mobilization to panels erected in 11 weeks. The 162 panels were erected using a 330 ton crane for panels weighing over 253,000 lbs. The pants leg panels with lids attached at the buildings NE and NW elevations provide a unique look while also constructed as tilt-up panels. All panels including ramp walls and electrical rooms were constructed as tilt-up panels.

 
Main banner image for I-4 Logistics

Project Location

Seffner, FL
United States

TILT-UP ACHIEVEMENT AWARD

The Tilt-Up Achievement Awards were established to honor projects that use site-cast tilt-up concrete to introduce new building types, advance industry technology and provide unique solutions to building programs. Winning entries illustrate the variety, beauty, and flexibility of tilt-up construction.

ACHIEVEMENT

2019

The world’s greatest tilt-up structures are featured by the TCA as Tilt-Up Achievement Award Winners. Learn more >

Project Images

Search Project Database

TILT-UP TODAY MAGAZINE / PROJECTS IN THE NEWS

Project Team (TCA Members)

General Contractor:
 
Concrete Contractor:
Carr and Sons Masonry
Architect:
 
Engineer:
Leviat
Suppliers:
Leviat
Photographer(s):

Project Specifics

Project Category:
Distribution
Building Types:
Distribution Center
Finishes:
Paint (Textured)
Features:
Cantilevered Panels
Embedded Items
Reveals
Shadow Panels
Insulation:
Environmental:
LEED Certified
Number of Floors:
1
Number of Panels:
162 panels
Tilt-Up Wall Area:
2,052 sq ft (191 sq m)
Total Floor Area:
515,000 sq ft (47,844 sq m)
Project Footprint:
425,000 sq ft (39,483 sq m)
Tallest Panel:
53 ft 11 in (16.43 m)
Heaviest Panel:
253,810 lbs (115,126 kg)
Tallest Cantilever:
57 ft 11 in (17.65 m)
Longest Spandrel:
59 ft 11 in (18.26 m)