Marathon Petroleum Corporation Central Control Building

The 68,000-square-foot, three-story Central Control Building was constructed as the cornerstone of the company's safety program and is the control facility for every processing unit at the Texas City Plant Site. The walls facing the refinery are 12-inch-thick concrete with two layers of rebar to create blast-resistance capacity.The building's curviliear appearance, constructed of straight wall segments, helps avoid building over the 138 kVA electrical duct bank and adds architectural interest.

 
Main banner image for Marathon Petroleum Corporation Central Control Building

Project Location

Texas City, TX 77590
United States

TILT-UP ACHIEVEMENT AWARD

The Tilt-Up Achievement Awards were established to honor projects that use site-cast tilt-up concrete to introduce new building types, advance industry technology and provide unique solutions to building programs. Winning entries illustrate the variety, beauty, and flexibility of tilt-up construction.

ACHIEVEMENT

2016

The world’s greatest tilt-up structures are featured by the TCA as Tilt-Up Achievement Award Winners. Learn more >

Project Images

TILT-UP TODAY MAGAZINE / PROJECTS IN THE NEWS

Project Team (TCA Members)

General Contractor:
 
Concrete Contractor:
 
Architect:
 
Engineer:
 
Suppliers:
 
Photographer(s):

Project Specifics

Project Category:
Production/Manufacturing
Building Types:
Finishes:
Features:
Insulation:
Environmental:
Number of Floors:
0
Number of Panels:
82 panels
Tilt-Up Wall Area:
44,985 sq ft (4,179 sq m)
Total Floor Area:
67,946 sq ft (6,312 sq m)
Project Footprint:
17,697 sq ft (1,644 sq m)
Tallest Panel:
61 ft 6 in (18.75 m)
Widest Panel:
18 ft 0 in (5.49 m)
Largest Panel:
1,107 sq ft (102.8 sq m)
Heaviest Panel:
172,000 lbs (78,018 kg)
Longest Spandrel:
12 ft 0 in (3.66 m)