All panels had to be cast on a temporary casting bed then walked up a slight incline to be placed on foundations that were five feet below sub-grade. Combined with the panel height and weight, lifting the panels off the temporary casting bed was a challenge, even with a 300-ton crawler crane. The required rigging length did not allow the panel to be turned once it was picked off the bed due to clearance with the main bar and the crane boom. All panels had to be erected and braced from the inside face due to utilities and an adjacent bridge outside the property line. Erection sequence and temporary brace planning were critical in maintaining a safe work environment.
Panel-to-panel connections were welded daily to help brace the panels against high winds during hurricane season. The required mitered corners along with a 1.5-inch deep form liner (large staggered block pattern) on a 78-foot-tall panel also created a challenge.
Fort Myers Beach, FL 33931
United States
The Tilt-Up Achievement Awards were established to honor projects that use site-cast tilt-up concrete to introduce new building types, advance industry technology and provide unique solutions to building programs. Winning entries illustrate the variety, beauty, and flexibility of tilt-up construction.
ACHIEVEMENT
2012
The world’s greatest tilt-up structures are featured by the TCA as Tilt-Up Achievement Award Winners. Learn more >