Carlisle Evangelical Free Church

2013 TCA Tilt-Up Achievement Award - Spiritual Division

Article tools: Coming soon!

The CEFC had a humble beginning, holding worship services first in spaces borrowed from a senior center and then moving to a pre-engineered facility. When it finally came time to build a new facility to accommodate their growing congregation, the church knew they didn't want a metal building, but metal seemed to be the only solution that would meet their budget.

Working together in an integrated project delivery (IPD) approach, however, SAA Architecture, LLC and Bay Contracting immediately decided that tilt-up was the answer. Tilt-up construction delivered a worship center that provided CEFC with more seating and stayed within the church's schedule and budget requirements. Solid concrete mass panels also allow for a very quiet structure, which is necessary as the worship center is located adjacent to the Carlisle Airport. Tilt-up construction provided architectural flexibility, too, as CEFC desired a theater seating format design that facilitated first rate audio and video systems.

To accommodate this and to reduce the building height, a 90-foot-long truss girder was run across the center of the structure to cut the roof span. Wall panel sizes (the tallest panel was 33 feet tall by 6 inches deep and the heaviest panel weighed 64,380 pounds) were minimized to reduce crane requirements and provide more design opportunities. To enhance the exterior aesthetics, various width panels were overlapped which allowed the horizontal components to take second place to the vertical. This effect was further enhanced with color and EFIS overlay. The concrete panels accepted the area of EFIS overlay seamlessly.

Project Specifics

Project Wall Area
19,216 sq ft
(1,785 sq m)
Project Footprint
18,919 sq ft
(1,758 sq m)
Tallest Panel
33 ft 6 in
(10.21 m)
Widest Panel
32 ft 2 in
(9.81 m)
Largest Panel
444 sq ft
(41.2 sq m)
Heaviest Panel
64,380 lbs
(29,202 kg)
Longest Spandrel Panel
30 ft 0 in
(9.14 m)

Participating TCA Members

SAA Architecture LLC
General contractor

About the TCA

Founded in 1986, the Tilt-Up Concrete Association (TCA) strives to improve the quality and acceptance of site-cast Tilt-Up construction, a method in which concrete wall panels are cast on-site and tilted into place. Tilt-Up construction is one of the fastest growing industries in the United States, combining the advantages of reasonable cost with low maintenance, durability, speed of construction and minimal capital investment. At least 10,000 buildings, enclosing more than 650 million square feet, are constructed each year using this construction method.

Follow Us

We use LinkedIn, Twitter and YouTube to disseminate information about the Tilt-Up industry, gain new members and inform developers, owners and architects about the benefits of using Tilt-Up.

Popular Links

The following bookmarks jump to the most popular destinations on this site.